Buyer’s Guide

What the July 2026 Safe Harbor Deadline Means for Your Panel Order

1000containers Team, November 20, 2026, 7 min read

Your project’s beginning of construction date now does as much to protect your solar tax credit as the equipment you put on the roof or in the field. If you are also trying to qualify for the domestic content bonus, the two deadlines move together, and a bulk panel order placed at the wrong time can put both at risk.

Why July 4, 2026 is on every EPC’s calendar

Under the One Big Beautiful Bill Act, a solar project that begins construction after July 4, 2026 generally has to be placed in service by December 31, 2027 to claim the Section 48E investment tax credit at all. Starting construction on or before July 4, 2026 avoids that compressed deadline and lets you rely on the standard continuity safe harbor instead.

When construction begins

Placed-in-service deadline

Before 2026

December 31, 2029

January 1, 2026 through July 4, 2026

December 31, 2030

After July 4, 2026, or the start test isn’t met by then

December 31, 2027, or no credit for the facility

Physical work test vs. the 5% cost safe harbor

Before September 2, 2025, a developer of any size could use either the 5% cost safe harbor, paying or incurring at least 5% of total project cost, or the physical work test to establish beginning of construction. IRS Notice 2025-42 narrowed that as of September 2, 2025: projects larger than 1.5 MW AC must now use the physical work test. Only facilities at or under 1.5 MW AC can still rely on the 5% cost safe harbor.

The physical work test requires a binding contract plus work of a significant nature, performed on site or off site, such as a supplier beginning fabrication of racking or a transformer built specifically for your project under contract. A purchase order by itself, without that physical work component, generally will not satisfy this test for larger projects.

What your bulk panel order needs to look like to count

A signed module purchase order is not automatically a beginning of construction event. For a project at or under 1.5 MW AC relying on the 5% safe harbor, the cost has to be paid or incurred under your tax accounting method and tied specifically to your project, not treated as a general deposit against future, unspecified orders.

Many accrual-method buyers lean on the economic performance rules: paying for modules and having them delivered within a defined window after payment, commonly cited as roughly 105 days, can support treating the cost as incurred on the payment date rather than the delivery date. For the physical work test required above 1.5 MW AC, a module purchase order alone is generally not enough on its own; it has to be paired with qualifying physical work under a binding contract.

Documentation your tax team and lender will want

  • An executed purchase contract that names the specific project, not a general supply agreement

  • Project-specific invoices and proof of payment, dated and traceable to that contract

  • Proof of title transfer and delivery records tying the shipment date back to the payment date

  • Serial number or lot tracking that links the physical modules received to the contract line items

  • A clear cost allocation showing the module spend as a share of total project cost

Frequently asked questions

Does a deposit on a bulk panel order automatically start construction for ITC purposes?

Not by itself. A deposit has to be tied to a binding, project-specific contract and, depending on your project size, paired with either the 5% cost test or qualifying physical work. A general deposit held against future allocation decisions is unlikely to qualify on its own.

Does the July 4, 2026 date also affect the domestic content bonus?

The domestic content requirements run on a related but separate timeline tied to when your project begins construction, with the required domestic cost percentage changing by year. Confirm both dates with your tax advisor, since a module order can affect your standing on each one differently.

My project is over 1.5 MW AC and I paid a deposit under the 5% rule before September 2025. Am I still covered?

IRS Notice 2025-42 applies going forward from September 2, 2025. Beginning of construction established under the prior rules before that date generally is not undone by the later notice, but this is exactly the kind of fact pattern to confirm directly with your tax counsel.

None of this is tax advice, and your CPA or tax counsel should confirm how these rules apply to your specific project and placed-in-service timeline. What 1000containers can do is make sure the module side of your documentation holds up: project-specific invoices, serial-number tracking, and delivery timed to your payment date. See current inventory and request a quote.

Subscribe to our newsletter for solar industry and inventory updates

© 2026 1000containers Holdings LLC.

Subscribe to our newsletter for solar industry and inventory updates

© 2026 1000containers Holdings LLC.